SAP ECC EHP8 — Plano de Cobertura de Testes

Baseado nas definições do QA Agent • Context Engineering Methodology

13 Módulos ~180 T-codes 32 Tipos de Teste 24 Integrações 7.000–9.000 Test Days

Visão Geral

13
Módulos SAP ECC
~180
T-codes mapeados
32
Tipos de teste
24
Pontos de integração
6
Fases de execução
~8k
Test days estimados

Os 32 Tipos de Teste

#Tipo de TesteManual %Auto %Cenários/MóduloPrioridade SAP ECC
1Unit Testing10%90%15–25Medium
2Integration Testing40%60%25–40CRITICAL
3System Testing60%40%30–50CRITICAL
4UAT95%5%40–60CRITICAL
5Regression Testing20%80%50–80CRITICAL
6Performance / Load Testing5%95%8–15High
7Stress Testing2%98%5–10Medium
8Security Testing50%50%20–35CRITICAL
9Smoke Testing30%70%10–15CRITICAL
10Sanity Testing50%50%8–12High
11End-to-End Testing70%30%15–25CRITICAL
12Data Migration Testing40%60%20–35CRITICAL
13Interface Testing30%70%15–25High
14Negative Testing35%65%25–40High
15Boundary Value Testing25%75%15–30High
16Equivalence Partitioning30%70%12–20Medium
17Configuration Testing55%45%30–50CRITICAL
18Compatibility Testing40%60%5–10Medium
19Usability Testing85%15%15–25Medium
20Accessibility Testing50%50%8–15Medium
21API Testing20%80%15–30Medium
22Database Testing25%75%20–30High
23Recovery Testing50%50%8–12High
24Failover Testing60%40%5–10High
25Parallel Testing50%50%20–40CRITICAL
26Conversion Testing35%65%15–25High
27Authorization / Role Testing70%30%25–40CRITICAL
28Business Process Testing65%35%20–35CRITICAL
29Exploratory Testing100%0%10–20High
30Mutation Testing5%95%10–15Optional
31Contract Testing20%80%12–20Medium
32Chaos Testing5%95%5–10Optional

Esforço por Módulo

MóduloT-codesTest Days EstimadosTipos mais críticos
FI — Financial Accounting~15~650Integration + UAT + Parallel
CO — Controlling~14~550Integration + Config + E2E
MM — Materials Management~17~750Data Migration + Integration
SD — Sales & Distribution~16~750System + UAT + E2E (O2C)
PP — Production Planning~15~700Integration + Performance (MRP)
PM — Plant Maintenance~14~400Integration + Business Process
QM — Quality Management~15~500Integration + Config + Block Logic
HR/HCM~14~650Security + Data Migration + Payroll
PS — Project System~14~450System + Business Process
WM — Warehouse Management~14~750Integration + System + UAT
BW/BI~12~600Integration + Performance + DB
TM + GRC~14~500Security + Interface
TOTAL~1807.000–9.000Integration + UAT (maiores esforços)

Fases de Execução

FaseSemanasTipo PrincipalFoco
1 — Unit1–4Unit TestingCustomizações ABAP, user exits, validações
2 — Integration5–12Integration + InterfaceFluxo entre módulos (MM→FI, SD→FI, PP→CO)
3 — System13–20System + E2E + ConfigProcessos completos, regras de negócio
4 — UAT21–28UAT + Business ProcessValidação com usuários, sign-off
5 — Regression29+ (contínuo)Regression + SmokePós-patch, estabilização pré-go-live
6 — ProduçãoGo-Live ±2 semParallel + Sanity + DataValidação paralela com legado